What damages are available in a South Carolina construction defect case?
Depending on the circumstances, compensation may include the cost of repairing the defect, loss in property value, water damage, mold remediation, and other related losses. A property owner may also be able to seek damages for loss of use. If the defect causes personal injury, additional damages may be available, such as compensation for medical […]
Can multiple parties be held liable for the same construction defect?
Yes. Depending on the cause of the defect, potentially responsible parties may include general contractors, subcontractors, architects, engineers, or manufacturers of defective materials. The responsibility of each party depends on the evidence and applicable law. An attorney can help identify liable parties and assess potential claims against them.
Can I file a construction defect claim if I purchased the property from someone else, not the original builder?
Possibly. Depending on the defect, the available legal grounds, and the time since construction was completed, a subsequent property owner may have a claim. South Carolina’s statute of repose generally applies regardless of who currently owns the property. An attorney can review the purchase history, warranties, and timeline to determine if a claim is possible.
Does South Carolina require me to give the builder a chance to fix the defect before I can sue?
In many residential construction defect cases, South Carolina law requires homeowners to provide written notice of the claim and give the contractor an opportunity to inspect and respond before filing a lawsuit. Separate notice-and-cure rules apply to nonresidential construction. The requirements and deadlines depend on the type of property and claim, so homeowners should review […]
How Long Do I Have to File a Construction Defect Claim in South Carolina?
Depending on the type of claim, South Carolina generally allows three years to file a claim after a construction defect is discovered or reasonably should have been discovered. However, a separate statute of repose generally sets an eight-year limit from the substantial completion of construction, with certain exceptions. The right-to-cure process may also affect the […]